Week 5 of construction has us moving along swiftly and on schedule! We are happy to report that construction on Pendleton Street started promptly on Monday morning and we are making good progress. Our team is currently preparing the area for larger sewer lines and a buried grease trap. Once this is completed, the crew will move on to laying the foundation for the new Shop For Me curbside pickup and café.
Additionally, work has continued in the basement. This week, we have started framing out new areas for the Meat Department preparation and the production area for Prepared Foods. We are excited about these developments and look forward to sharing the finished results!